Serbia’s €153 million southern gas corridor advances as supply diversification faces financing, capacity and 2028 completion risks

Supported byClarion Owners Engineers

Serbia is moving towards construction of a €153 million gas interconnector with North Macedonia, opening a potential new supply route from Greece and international LNG markets, but the project’s commercial value will depend on synchronized cross-border infrastructure, long-term supply contracts and the ability to attract sufficient gas volumes to justify investment.

The first pipeline sections have arrived in southern Serbia, allowing preparations for installation along an initial five-kilometre stretch near Vranjska Banja, according to Energy Minister Dubravka Đedović Handanović.

Supported byVirtu Energy

The Serbian section will extend approximately 145 kilometres, with a planned annual transmission capacity of 1.5 billion cubic metres (bcm). Pipes covering 15 kilometres are expected to be delivered by the end of October.

The government originally targeted completion in the first quarter of 2028, but land expropriation and construction coordination remain unresolved risks. North Macedonia’s connecting section is now scheduled for completion in the final quarter of 2028, potentially delaying the full commercial operation of the route.

The investment marks another stage in Serbia’s effort to diversify gas supplies beyond its established eastern connections, following the commissioning of the Serbia–Bulgaria interconnector and the development of additional regional transmission projects.

Supported byClarion Energy

However, new pipeline capacity does not automatically guarantee access to competitively priced gas. Serbia will need to secure supplies, transportation rights and commercially viable demand before the southern corridor can deliver its intended economic benefits.

A new route from Greece to the Serbian market

The planned pipeline will connect Serbia’s gas transmission system near Orljane, south of Niš, through Leskovac and Vranje to the North Macedonian border.

Supported by

The project includes approximately 97 kilometres of upgraded transmission infrastructure between Orljane and Vranje and around 47 kilometres connecting Vranje with North Macedonia.

On the North Macedonian side, the new pipeline will extend approximately 22.4 kilometres from the Klečovce area to the Serbian border.

The Macedonian project has an estimated investment cost of approximately €29.6 million, including financing supported by the European Bank for Reconstruction and Development and the Western Balkans Investment Framework.

Combined, the Serbian and North Macedonian investments represent an infrastructure programme of approximately €183 million, excluding the wider Greek and North Macedonian network developments required to establish the complete southern supply route.

The strategic objective is to connect Serbia with natural gas entering southeastern Europe through Greece, including LNG infrastructure and supplies transported through the Southern Gas Corridor.

Access to the Trans Adriatic Pipeline and the wider Trans-Anatolian gas network could provide additional commercial opportunities, subject to available capacity and contractual arrangements.

For Serbia, the project would create another physical entry route and reduce dependence on any single transmission corridor.

Its effectiveness will depend on whether suppliers can deliver sufficient gas through all connecting systems at prices competitive with existing import arrangements.

Supply diversification is not the same as supplier diversification

Serbia’s gas policy has traditionally relied heavily on Russian supplies, supported by regional pipeline infrastructure and underground storage.

The Serbia–Bulgaria interconnector, commissioned in late 2023, created an additional route capable of transporting approximately 1.8 bcm annually.

The southern connection with North Macedonia would add another 1.5 bcm of nominal annual transmission capacity.

Together, these routes could substantially increase Serbia’s technical flexibility in sourcing imported gas.

However, physical capacity and actual supply diversification are different concepts.

A pipeline can transport gas from multiple commercial suppliers, but its existence does not guarantee that those suppliers will offer attractive prices or commit sufficient volumes.

Gas entering Greece through LNG terminals is exposed to international LNG prices, shipping costs, terminal charges and competition with other European buyers.

Azerbaijani gas transported through the Southern Gas Corridor is subject to upstream production availability, existing long-term contracts and transmission capacity.

Additional cross-border transportation tariffs may also affect the final delivered price.

For Serbian industrial consumers, the commercial value of the new route will therefore be measured by delivered gas costs rather than the number of available interconnectors.

The 2028 timetable creates investment uncertainty

The project faces an important implementation challenge because the Serbian and North Macedonian sections are advancing on different schedules.

Serbia has identified the first quarter of 2028 as its original completion target, although the government acknowledges that land expropriation must be finalized to maintain progress.

North Macedonia has contracted the construction of its section, with completion planned for the fourth quarter of 2028.

The Greece–North Macedonia interconnector is expected to become operational during 2027.

This sequence creates a potential period in which parts of the corridor are technically completed but cannot yet support continuous commercial flows.

For infrastructure investors, such timing differences can influence financing costs, construction expenditure and the start of regulated transmission revenues.

A completed pipeline that cannot operate because an adjoining section remains unfinished may still incur maintenance, financing and operational-readiness costs.

The financial consequences depend on the project’s funding structure and the contractual arrangements governing commissioning.

Coordinated technical testing, gas-quality standards, metering, pressure management and operational agreements will be essential before the route can enter commercial service.

Transmission capacity must be matched with demand

The planned annual capacity of 1.5 bcm is significant in relation to Serbia’s gas market.

However, the economic justification for the investment depends on how much of that capacity is actually booked and utilized.

Pipeline infrastructure involves substantial fixed costs, including construction, compressor and pressure-management requirements, maintenance, monitoring and system operation.

If throughput remains substantially below design capacity, the effective infrastructure cost per transported cubic metre can increase.

At full nominal utilization, the Serbian investment of €153 million represents approximately €102 of initial capital expenditure per annual cubic metre of transmission capacity.

That ratio is not a transportation tariff or a measure of project profitability. It simply illustrates the relationship between capital expenditure and designed throughput.

A more meaningful financial assessment would require forecasts of annual booked capacity, regulated revenues, operating costs, financing terms and asset life.

At 50% utilization, the pipeline would transport approximately 750 million cubic metres annually.

At 25%, throughput would fall to approximately 375 million cubic metres.

Those scenarios demonstrate why long-term capacity commitments and credible demand forecasts are important to infrastructure bankability.

The project may still generate strategic value through supply security even when utilization is limited, but that benefit must be distinguished from direct commercial returns.

Industrial demand could determine the corridor’s economics

Southern Serbia has an industrial base that could benefit from more reliable gas supply and improved transmission infrastructure.

Potential demand comes from manufacturing, food processing, district heating, industrial boilers and gas-fired electricity generation.

However, additional gas demand will depend on the competitiveness of natural gas relative to electricity, biomass and other energy sources.

Industrial consumers are increasingly exposed to European carbon regulations, energy-efficiency requirements and pressure to reduce emissions.

For some manufacturing processes, gas may remain an important transition fuel. For others, electrification could become more economically attractive.

This creates uncertainty for long-term demand forecasts.

A pipeline designed for several decades of operation must be evaluated against changing industrial energy consumption rather than assuming continuous growth in gas use.

The development of southern Serbia’s industrial base, together with the potential expansion of gas distribution networks, will therefore influence the investment’s commercial performance.

Niš gas-fired power project adds another demand dimension

The planned gas-fired electricity project near Niš, associated with cooperation between Serbia’s Elektroprivreda Srbije (EPS) and Azerbaijan’s SOCAR, could provide an additional source of gas demand.

The project has been discussed as a combined-cycle gas-fired power plant intended to strengthen electricity supply flexibility and support the integration of renewable generation.

Its potential relevance to the southern gas corridor is considerable, given the geographic proximity of Niš to the planned transmission route.

However, the commercial relationship between the two investments should not be assumed.

The power plant’s final capacity, investment structure, gas supply arrangements, construction timetable and operational profile will determine its actual transmission requirements.

If the plant proceeds, it could support gas demand and provide electricity during periods of low renewable generation or elevated market prices.

Its profitability would depend on the spread between electricity revenues and gas, carbon and operating costs.

A gas-fired plant may also require flexible gas delivery rather than constant annual volumes, creating additional requirements for storage and balancing.

For financiers, the central question would be whether the electricity project and the gas infrastructure have sufficiently aligned contractual and operational arrangements.

Storage and existing connections remain essential

Serbia’s energy security strategy also depends on underground gas storage and existing cross-border infrastructure.

In October, the government reported gas reserves of approximately 707 million cubic metres across available storage arrangements.

Storage provides flexibility during winter demand peaks, temporary supply interruptions and periods of elevated international prices.

However, storage and import diversification perform different functions.

Additional pipelines can provide alternative physical delivery routes, while storage can supply gas when imports are interrupted or insufficient.

The economic benefit is strongest when both systems operate within a coordinated procurement and balancing strategy.

The planned southern corridor should therefore be assessed alongside the Bulgaria interconnector, Serbia’s existing transmission network and proposed connections with Romania.

The objective is not necessarily to maximize the number of pipelines, but to ensure that the combined system offers reliable supply at an acceptable long-term cost.

Regional competition could shape gas flows

The southern interconnector forms part of a broader effort to improve gas connectivity between Greece, Bulgaria, North Macedonia and Serbia.

Energy ministers from the four countries reaffirmed their support for the Vertical Gas Corridor during meetings in Belgrade on October 6.

The initiative aims to improve the movement of gas from southeastern European entry points towards Central Europe and the Western Balkans.

Serbia and North Macedonia have joined the corridor initiative through their transmission system operators.

However, multiple countries are simultaneously developing infrastructure intended to attract similar gas flows.

This creates opportunities for regional integration but also potential competition between routes.

Transmission tariffs, capacity allocation and the availability of competitively priced supplies will influence which corridors attract commercial users.

A technically available route may remain underutilized if an alternative offers lower total transportation costs.

For Serbia, the priority should be to secure commercially attractive access to gas rather than rely solely on the strategic importance of the infrastructure.

Financing must reflect both commercial and security benefits

The southern gas interconnector combines conventional infrastructure investment with broader energy-security objectives.

The €153 million Serbian investment is intended to create a new transmission route, while the Macedonian section benefits from international development financing.

The financial model must account for construction expenditure, financing costs, regulated revenues, operational expenses and the potential value of supply diversification.

A purely commercial assessment may produce different conclusions from a national energy-security evaluation.

An underutilized pipeline can still provide substantial strategic value during a supply interruption.

However, that value does not eliminate the need for transparent financing assumptions and realistic demand forecasts.

Public authorities and infrastructure operators should distinguish between costs recovered through transmission tariffs and costs justified by wider security-of-supply benefits.

The allocation of these costs will matter for industrial gas consumers, utilities and ultimately the competitiveness of Serbia’s economy.

The next test is securing gas, not installing pipes

The delivery of the first pipes represents a tangible construction milestone for a project that has spent years in planning.

It also moves Serbia closer to establishing another physical connection with the gas infrastructure of southeastern Europe.

But the investment’s success will depend on several developments beyond construction.

The Macedonian and Greek sections must become operational, cross-border capacity must be available, and commercial suppliers must be willing to deliver gas at competitive prices.

Industrial consumers and potential power generators must also generate sufficient demand to support meaningful utilization.

For Serbia, the southern interconnector offers a credible opportunity to strengthen gas supply security and improve its negotiating position in regional energy markets.

Yet its €153 million construction cost and 1.5 bcm annual capacity will only translate into durable economic benefits if the country can combine physical infrastructure with competitive procurement, reliable cross-border access and commercially sustainable gas consumption.

The first pipes have arrived. The more difficult investment test is whether Serbia can secure the gas volumes and contracts needed to make the new corridor economically valuable once construction is complete.